4. Precedence constraints
BasicMediumLesson 4 of 13
Arrows between tasks that decide what runs next:
- Success (green), Failure (red), Completion (blue — either way).
- Expression or Expression and Constraint — e.g. run only if
@[User::RowCount] > 0. - Multiple incoming constraints: Logical AND (all must be satisfied — default) or Logical OR (any one).